CRBRP: Fuel Handling
1981? film, with transcript
Catalog description: Fuel handling equipment for the Clinch River Breeder Reactor Project.
This is film 7479943 in our catalog.
Show transcript
| 00:00 | The Clinch River Breeder Reactor Project began in June 1970 when the United States Congress |
| 00:24 | authorized the Atomic Energy Commission to undertake the design, construction and operations |
| 00:29 | of the nation's first liquid metal fast breeder reactor demonstration plant. |
| 00:35 | The project was established with the principal objectives of, |
| 00:39 | first, demonstrating that the liquid metal fast breeder can operate reliably and safely, |
| 00:45 | and, second, demonstrating the economics of the fast breeder reactor cycle. |
| 00:53 | This is the Clinch River, Oak Ridge, Tennessee, |
| 00:57 | future site of the Clinch River Fast Breeder reactor. |
| 01:01 | This 1364 acre site is owned by the United States government |
| 01:06 | and is managed by the Tennessee Valley Authority. |
| 01:11 | The Clinch River Reactor is a sodium-cooled, fast breeder nuclear power plant |
| 01:17 | designed for a net electrical output of 350 megawatts. |
| 01:22 | The major systems of the plant are the reactor, heat transport, steam generator and feed water systems, turbine generator, fuel |
| 01:39 | handling system and various auxiliary systems required to support plant |
| 01:44 | operation and maintenance. In a joint effort by government, utilities and |
| 01:50 | industry, the design, development and fabrication of the plant and its |
| 01:54 | components are well underway. Project participants from industry include the |
| 02:00 | Atomics International Division of the Rockwell International Energy Systems |
| 02:03 | Group, Westinghouse, General Electric, Burns and Rowe, and Stone and Webster. One |
| 02:11 | of Atomics International's responsibilities is the design and |
| 02:15 | procurement of the reactor fuel handling system and associated components. The |
| 02:21 | The reactor system requires periodic refueling, nominally once a year to replenish the supply |
| 02:26 | of fuel. |
| 02:28 | The fuel handling system provides the facilities and equipment necessary to accomplish the |
| 02:33 | yearly refueling operations and all associated functions, such as fuel handling within the |
| 02:39 | reactor vessel, fuel handling and storage outside the vessel, and shipping and receiving |
| 02:44 | operations on site. |
| 02:48 | handling operations take place in two buildings the containment building which houses the reactor |
| 02:54 | and the service building which contains fuel handling facilities and ancillary equipment |
| 03:01 | equipment and facilities located in the reactor containment building are limited to those involved |
| 03:07 | with fuel handling inside the reactor during shutdown they include the in-vessel transfer |
| 03:13 | machine referred to as IVTM for moving fuel within the reactor vessel and the |
| 03:19 | auxiliary handling machine or AHM for installing and removing the IVTM. The |
| 03:28 | IVTM is mounted on the smallest of the triple rotatable plugs which form the |
| 03:33 | closure head of the reactor. By rotating the three plugs the IVTM can be located |
| 03:41 | over any core position in the reactor. |
| 03:46 | The IVTM can then withdraw a spent assembly from the core |
| 03:51 | or insert a new assembly by vertical motions and grappling action. |
| 04:00 | Lateral movement of the core assembly within the reactor vessel |
| 04:04 | is accomplished by translation of the rotatable flux. |
| 04:11 | The majority of the fuel handling equipment and facilities is in the reactor service building, |
| 04:26 | which is adjacent to the reactor containment building. |
| 04:31 | Fuel handling facilities and equipment located in the service building include a sodium-filled |
| 04:36 | storage tank for temporary storage of spent fuel, a fuel handling cell for inspection |
| 04:42 | and handling of spent fuel assemblies, and facilities for receiving new fuel and for |
| 04:48 | shipping spent fuel. |
| 04:52 | The X-Vessel Storage Tank, or EZST, is a 20 foot diameter by 45 foot deep sodium vessel. |
| 05:01 | contains a two-tier rotatable turntable capable of holding 650 fuel assemblies. |
| 05:07 | The assemblies are stored in sodium-filled pots with two pots stacked |
| 05:12 | one above the other in each storage tube. Access to the storage positions is |
| 05:18 | obtained through nine openings in the closure head. The turntable is rotated to |
| 05:23 | gain access to each storage position in each row. The storage tank also contains |
| 05:30 | a number of dry argon gas-filled preheat tubes located in the upper tiers where |
| 05:36 | cold assemblies are placed for preheating prior to immersion in the hot |
| 05:39 | sodium. The fuel handling cell is a small hot cell with three stations, a |
| 05:46 | maintenance station, a fuel examination station, and a spent fuel loading station. |
| 05:53 | Selected fuel assemblies can be visually inspected and dimensionally measured in |
| 05:58 | this facility. In addition, spent fuel assemblies are prepared for shipment off-site. Prior to loading |
| 06:06 | operations, a shipping cask is positioned and sealed below an opening in the floor of the cell. |
| 06:12 | The fuel assembly can now be transferred to the cask through the floor opening. |
| 06:19 | In addition to the equipment and facilities located in the containment and service buildings, |
| 06:24 | fuel movement between buildings and facilities is accomplished using the Ex-vessel Transfer Machine, |
| 06:30 | or EVTM, a heavily shielded and cooled transfer machine mounted on a gantry. |
| 06:37 | The EVTM has a central eight inch diameter cavity for carrying a fuel assembly. This cavity |
| 06:44 | contains an argon atmosphere. Due to their negligible heat production new fuel assemblies |
| 06:50 | are handled bare, but spent fuel must be carried in sodium filled pots to |
| 06:55 | adequately cool the fuel assembly. The sequence for handling fuel begins with |
| 07:02 | the arrival of new fuel on site in lightly shielded containers. Once the |
| 07:08 | containers and their contents have been checked, a shipping container is placed |
| 07:12 | in one of the two new fuel unloading stations by the service building crane. |
| 07:21 | Here the shipping container atmosphere is changed from air to argon. |
| 07:26 | After the container has been inerted, the EVTM picks up the assembly and transfers it to a |
| 07:32 | special preheat station in the EDST where it is preheated in argon to 400 degrees Fahrenheit. |
| 07:39 | After preheat is complete, the assembly is transferred by the EVPM from the preheat |
| 07:46 | station to a sodium-filled pot in one of the storage positions in the EVST. The fuel remains |
| 07:53 | in this position until the reactor is shut down and made ready for replacement of fuel assemblies. |
| 07:58 | After reactor shutdown, refueling preparations begin by removal of the large diameter equipment |
| 08:05 | hatch to allow movement between the containment and service building. Also, the IVTM is then |
| 08:12 | installed in the reactor head by means of the AHM and the building crane. |
| 08:35 | Floor valves are positioned over access openings to the reactor and the ex-vessel storage tank. |
| 08:43 | The reactor is now ready to be refueled. |
| 08:47 | The IVTM, in conjunction with the rotatable plug, removes the spent fuel assembly from |
| 08:53 | the core and deposits it in an empty pot located in a transfer position outside the core but |
| 09:00 | still within the reactor vessel. |
| 09:02 | At the same time, the EVTM removes the new fuel assembly from the EVST and transports |
| 09:09 | the assembly to the reactor. |
| 09:12 | By sealing the EVTM to a special port in the head of the reactor, the EVTM can lower the |
| 09:18 | new fuel assembly into a second transfer position in the reactor, within reach of the IVTM. |
| 09:25 | During the same attachment operation to the reactor head, the EVTM removes the spent fuel |
| 09:31 | assembly in the first transfer position. |
| 09:36 | While the EVTM transports the spent fuel to the storage vessel, the IVTM |
| 09:42 | completes the cycle by installing the new fuel assembly into the open core |
| 09:47 | lattice. These operations are repeated until the reactor core has been refueled. |
| 09:56 | When refueling is completed, the reactor is brought back online. After the spent |
| 10:03 | fuel in the storage tank has decayed for approximately 100 days, the assemblies |
| 10:08 | are ready to be shipped off-site. A fuel assembly is transferred by the EVTM in a |
| 10:14 | sodium-filled pot from the storage tank to the fuel handling cell. |
| 10:26 | The fuel assembly is removed from the pot by means of a gas-cooled grapple for loading into the shipping cask. |
| 10:34 | Capabilities exist in the cell to visually and dimensionally inspect the assembly. |
| 10:40 | A spent fuel shipping cask is brought into the service building by a special railroad car, |
| 10:45 | moved to a position beneath the fuel handling cell, and sealed to the loading port. |
| 10:51 | Fuel can now be transferred from the cell to the shipping cask. |
| 10:57 | When the cask is full, it is disconnected from the fuel handling cells, inspected for |
| 11:02 | conformance to shipping regulations, and then transported by a rail to a fuel reprocess. |
| 11:11 | The Quench River's fuel handling system is well on its way to becoming a reality. |
| 11:17 | The necessary development testing has been complete, as has most of the engineering design. |
| 11:26 | Many of the major fuel handling components are being fabricated and some are presently being proof tested. |
| 11:38 | The IVTM was designed and fabricated by Atomics International at Canoga Park, California. |
| 11:46 | Component tests were conducted between 1974 and 1977 to support the IVTM design phase. |
| 11:53 | These tests included environmental testing of the grapple drive rod seals, performance testing of |
| 12:02 | the drive motor, braking system and gear trains, and kinematic testing of the grapple under adverse |
| 12:08 | conditions. Manufacturing began in August of 1977 with machining and assembly of the 43-foot long |
| 12:17 | in-vessel sub-assembly on the grapple. A drive tower structure was fabricated to |
| 12:25 | house the grapple actuator mechanism. Assembly of pneumatic and electrical |
| 12:30 | components on the equipment bay structure completed the last major |
| 12:34 | sub assembly. In May of 1979, the major sub-assemblies were delivered to the |
| 12:45 | the Energy Technology and Engineering Center located at Rockwell International's Santa |
| 12:50 | Susana Field Laboratory. Here, the IVTM was assembled into a 65-foot high machine to undergo |
| 12:59 | a testing program which would be equivalent to five complete core refuelers. The testing |
| 13:08 | program was divided into two stages. The first stage, completed in July of 1979, was a dry |
| 13:16 | checkout to verify the IVTM's capability to withdraw and insert the core assemblies through |
| 13:22 | the full range of misalignments and loads expected during refueling operations. The |
| 13:28 | second stage, performance testing the IVTM in a hot sodium environment, will begin in |
| 13:34 | November of 1979. During this stage the IVTM computer controls will be checked |
| 13:40 | out concurrently with the testing of the machines. After the IVTM has completed |
| 13:46 | its performance test, it will undergo any necessary refurbishment and then will be |
| 13:51 | shipped to the Oak Ridge site. After extensive developmental testing of key |
| 13:58 | features of the EVTM, final design was completed and procurement was initiated. |
| 14:05 | In 1973 and 1974, several small-scale tests investigated important heat |
| 14:12 | transfer parameters. These tests supported preliminary design decisions. |
| 14:18 | And in 1975, a full-scale test with a cooling system, cast body internals, and |
| 14:26 | and an electrically simulated fuel assembly confirmed the final design. |
| 14:32 | Currently, all long-lead forgings and castings for the EVTM are on hand, |
| 14:38 | including the grapple drive housing and cover, upper support module, viewport housing, |
| 14:44 | drift pan housing, closure valve body, and other major modules. |
| 14:50 | Once the remaining EVTM components have been manufactured |
| 14:54 | and the grapple and grapple drive proof test completed, |
| 14:58 | these sub-assemblies are scheduled to be shipped to a test site in Oak Ridge |
| 15:01 | for final performance testing of the full assembled machines. |
| 15:06 | The EVST, which is used for the storage of fuel assemblies, is well into fabrication. |
| 15:12 | The storage vessel and components were designed by Atomics International |
| 15:17 | and subcontracted to a wide range of industrial concerns for fabrication. |
| 15:22 | Four forgings were procured and delivered to Babcock and Wilcox, who will fabricate the major components. |
| 15:30 | The storage vessel support plan required one of the largest forgings made by Lavish Company at their Wisconsin plant. |
| 15:38 | Starting with a 336,000 pound heated steel engine, the general shape was formed by ring forging machines and then quenched in a water pool. |
| 15:47 | followed by tempering the steel in a heat-treating furnace. |
| 15:53 | The forging was then rough-machined to its 24-foot diameter |
| 15:57 | and delivered to Babcock and Wilcox's Mount Vernon, Indiana plant |
| 16:02 | for final machining and assembly. |
| 16:04 | At the Babcock and Wilcox plant, other EVST parts have been fabricated and assembled. |
| 16:12 | Steel plates have been rolled and welded into shell cores. |
| 16:15 | The vessel bottom head has been formed from smaller shaped pieces and final machined to |
| 16:23 | a smooth dished head. |
| 16:26 | The turntable grid plates for support of the 330 storage tubes have been drilled and machined |
| 16:33 | and the vessel closure head is presently being final machined. |
| 16:40 | Other EVST components are being fabricated by industry. |
| 16:44 | completion of these components they will be assembled with the Babcock and |
| 16:48 | Wilcox vessels for a final functional proof test before delivery of the |
| 16:53 | completed vessel to the Clink River site. |
| 17:00 | The fuel handling cell components are in various stages of design and development. |
| 17:06 | The in-cell crane, Howard manipulator and the master slave manipulators have |
| 17:12 | completed fabrication and have been tested at the Santa Susana Laboratories. |
| 17:17 | The equipment performed satisfactorily under mock-up situations. In the future, |
| 17:23 | these components will be assembled in a mock-up structure of the handling cell |
| 17:27 | of Santa Susana. There they will be used to confirm the operation of the other |
| 17:32 | shell equipment. Several mock-up components will be built and tested to |
| 17:37 | provide design information before fabrication of plant hardware. After |
| 17:43 | equipment has been checked out, the mock-up will be disassembled and shipped |
| 17:47 | to the Oak Ridge site as an operator training device. The individual fuel |
| 17:55 | handling equipment must be controlled as an integrated system. To do this, an |
| 18:00 | overall refueling control system has been designed, which includes three |
| 18:06 | inter-communicating mini computer. These computers have been procured and the software program has |
| 18:12 | been designed to enable the computers to perform their individual and combined functions. Tests |
| 18:19 | are currently underway to demonstrate their overall performance capabilities. |
| 18:25 | Over 80 percent of the fuel handling equipment has been designed and most of the major components are |
| 18:31 | in the process of fabrication. Components fully designed and ready for fabrication include the AHM, |
| 18:42 | floor valves and adapters, the EZTM gantry, the fuel handling cell maintenance and examination |
| 18:51 | equipment, and miscellaneous storage facilities. Progress has been substantial. |
| 18:59 | Through extensive component testing to support the design phase, |
| 19:03 | followed by confirmatory proof testing of plant hardware, fuel handling system components are verified to be safe and reliable before delivery to the plant. |
| 19:14 | The Clinch River components are well on their way toward completing the project. |